Avant-Garde have prepared / are preparing detailed project reports for the following projects.  These projects are captive power plants for the sponge iron / steel industry which are either connected to grid or installed for in-house captive power generation.

S.NoProjectCapacity
1Shyam Steel Ltd., West Bengal (Burdhwan)
(3 x 50 TPD Kilns WHRSG + FBC)
Grid paralleled inhouse use of Electric power.
5.00 MW
2Shyam Steel Ltd., West Bengal (Mangalpur)
(3 x 100 TPD Kilns WHRSG)
Grid paralleled inhouse use of Electric power.
8.00 MW
3Jai Balaji Sponge Ltd., West Bengal (Ranigunj)
(7 x 50 TPD Kilns WHRSG + FBC)
In-house usage of electric power.
12.00 MW
4Sri Ram Rupai Balaji Ltd., West Bengal
(4 x 100 TPD Kilns WHRSG + 1 CFBC boiler)
In-house usage of electric power .
30.00 MW
5Adhunik Corporation Ltd., West Bengal (Durgapur)
(3 x 100 TPD Kilns WHRSG + FBC)
Grid paralleled inhouse use of electric power
16.00 MW
6Ankit Steel Works Pvt.Ltd., West Bengal (Bankura)
(1 x 350 TPD Kilns WHRSG)
Grid paralleled inhouse use of electric power.
8.50 MW
7Electrosteel Castings Limited, Haldia, West Bengal
(2 Batteries of 34 coke ovens WHRSG) Grid paralleled inhouse use & export of electric power.
12.00 MW
8Neo Metallicks Ltd., Durgapur, West Bengal
(BFG based captive power plant-Stage-1)
4.50 MW
9Ma Chandi Durga Ispat Pvt. Ltd., Durgapur, West Bengal (2 x 100 TPD + 3 x 50 TPD Kilns WHRSG) In-house usage of electric power.8.50 MW
10Ma Chandi Durga Ispat Pvt. Ltd., Durgapur, West Bengal (2 x 100 TPD + 3 x 50 TPD Kilns WHRSG)
In-house usage of electric power.
40.00 MW
11Rashmi Ispat (I) Ltd.,  Midnapore dist., West Bengal 3 x 100 TPD kiln, WHSRG + 1 FBC boiler10.00 MW
12Bihar Sponge Iron Ltd., Jamshedpur,
(1 x 500 TPD kiln WHRSG + 1 x 100 TPD kiln WHRSG)
Grid paralleled export of power
18.00 MW
13Singhal Enterprises Pvt. Ltd., Chhatisgarh (Raigarh),
(4 x 100 TPD Kilns WHRSG + FBC)
Grid paralleled inhouse use of Electric power.
16.00 MW
14Satya Power and Ispat Ltd, Chhattisgarh
(2 x 100 TPD Kilns WHRSG + 1 AFBC)
Grid paralleled inhouse use of electric power.
12.00 MW
15Jai Balaji Jyothi Steels Ltd, Orissa (2 x 30MW)
(8 x 100 TPD Kilns WHRSG + 2 CFBC) in-house
usage of electric power with grid connection
60.00 MW
16Neepaz Metaliks Limited (Adhunik Group), Orissa
(5x100 TPD kilns WHRSG + 1 FBC boilers)
Grid parallelled inhouse use of power
34.00 MW
17Adhunik Alloys & Power Ltd., Jharkhand
(2 x 350 TPD Kilns WHRSG + 2 AFBC)
Grid paralleled inhouse use of electric power.
25.00 MW
18Sunvik Steel Private Ltd., Karnataka
(2 x 100 TPD Kilns WHRSG + 1 AFBC)
Grid paralleled inhouse use of electric power.
10.00 MW
19BMM Ispat Limited, Karnataka
(2 x 100 TPD kilns WHRSG + 1 FBC boilers)
Grid parallelled inhouse use of power
25.00 MW
20Gupta Metalicks & Power Ltd., Nagpur, Maharashtra
(4x100 TPD kilns WHRSG + 2 FBC boilers)
Grid parallelled inhouse use of power
40.00 MW
21Gallant Metal Limited, Gandhidham, Gujarat.
(3x100 TPD kilns WHRSG + 1 FBC boiler)
Grid parallelled inhouse use of power)
25.00 MW
22Bhatia International, Gummidipoondi, Chennai
Coke oven gas fired boilers (2 nos of 20 TPH)
9.00 MW
TOTAL428.50 MW
S.NoProjectCapacityFuel
1Kamachi Sponge Iron Ltd, Gummidipoondi, Tamil Nadu10 MWWaste Heat Recovery
2Kalyani Gerdau Steels Ltd., Tadipatri, Andhra Pradesh6 MWBlast Furnace gas
3Sunvik Steels Private Limited, Karnataka10 MWWHRB, Coal / Char / AFBC
4Dhruvdesh Metasteel Private Limited, Koppal, Karnataka10 MWCoal / kiln hot gas / AFBC
5Aarti Steels Ltd., Orissa (Phase – I )40 MWWashery rejects, coal, char /AFBC
6Adhunik Metalliks Ltd., Rourkela, Orissa2 X 17 MWCoal / Char / Washery Rejects / CFBC
7Action Ispat & Power (P) Ltd., Jharsuguda, Orissa12 MWCoal / Char / Washery Rejects
8OCL Limited, Orissa14 MWWashery Rejects / Coal/ Char
9OCL Ltd., Rajgangpur2 X 27 MWIndian Coal / Washery Rejects
10Aarti Steels Ltd.,   Phase -II, Orissa 50 MWChar / coal, washery rejects / CFBC
11MGM Steels Limited, Orissa8 MWKiln hot gas
12Rungta Mines Limited, Kamando, Orissa2 X 20 MWCoal / Dolochar & Hot Gas / AFBC
13Adhunik Ferro Alloys Ltd., Jamshedpur, Jharkhand 16 MWWaste heat recovery and AFBC
14AML Steel and Power (P) Ltd, Jamshedpur, Jharkhand9.6 MWWaste heat recovery
15Kohinoor Steels Ltd Jamshedpur, Jharkhand17 MWWaste heat recovery, Dolochar
16Rungta Mines Limited, Chaliyama, Jharkhand 2 X 20 MWCoal / Dolochar & hot gas / AFBC
17Gallant Metals Ltd., Gorakhpur, UP18 MWWaste heat recovery, Dolochar / coal / AFBC
18Shri Ramrupai Balaji Steels Ltd, Durgapur, West Bengal 2 X 25 MWWaste heat, recovery, Dolochar & Washery Rejects / CFBC
19Jai Balaji Sponge Iron Ltd., West Bengal 12 MWWaste heat recovery & AFBC
20Electro Steel Castings Ltd., West Bengal3.5 MWBFG  / Oil
21Neo Metaliks Limited, Kolkata 4.5 MWBFG
22Supersmelters Limited, West Bengal35 MWWHRB & Coal / Char / Washery / CFBC
23Ind Synergy Limited., Raipur 50 MWCoal / Char / Washery Rejects / CFBC
24Govind Ispat Ltd, Chhattisgarh15 MWWaste heat recovery and AFBC
25Shri Shyam Ispat (India) Private Limited, Chhattisgarh17 MWCoal / Kiln hot Gas / AFBC
26Gallant Metals Limited, Ahmedabad25 MWCoal / Kutch, Kutch Lignite / AFBC
27SWIL Ltd, Gujarat15 MWFurnace Oil
28Bhushan Power & Steel Limited2 X 8 MWCoke oven gas based waste heat recovery
29Bhushan Power & Steel Limited, Rengali, Orissa  130 MWCoal / Char / CFBC
30Gerdau Steels Ltd., Tadipatri, Andhra Pradesh15 MWCoke Oven Gas (WHRSG)
31Abhijeet Infrastructure Ltd, Jharkhand2 X 30 MWCoal / Char / Washery / CFBC
32Corporate Ispat alloys Limited, Saraikela, Jharkhand2 X 30 MWWHRB, Coal based / CFBC
33SPS Steel & Power Ltd., Jharsuguda, Orissa30 MW & 40 MWIndian Coal / Char / CFBC
34Singhal Enterprises., Chhattisgarh7.2 MWWaste heat recovery from sponge iron plant
35Salasar Steel & Power Ltd., Raigarh, Chattisgarh 63 MWWashery rejects / Char / Coal / CFBC
36Concast Ispat Limited, Rourkela18 MWWHRB, Coal based
37Rungta Mines Limited, Chaliyama20 MWWHRB, Coal based
38Rungta Mines Limited, Dhenkanal, Phase I25 MWWHRB, Coal based
39Rungta Mines Limited, Dhenkanal, Phase II35 MWWHRB. Coal based
40Rungta Mines Limited, Karakola20 MWWHRB, Coal based
41Rungta Mines Limited, Chaliyama, Jharkhand2 x 40MWWHRB, Coal based
42Rungta Mines, Kamando20 MWWHRB, Coal based
43Electrosteel Castings, Ltd, West Bengal5 MWWHRB, Coal based
Total1459.80MW
S.NoProjectCapacityFuel
1Bhushan Power & Steel Limited,  Rengali, Orissa8 MWCoal
2B.S. Sponge Private Limited 15 MWChar / Washery
3Chandil Power Private Limited 20 MWHot Kiln Gas & AFBC (Char/Washery)
4Sandeep Energy & Steel S.A. (SEAS), Mali, Africa25 MWCoal
5Bhatiya International15MWCoke oven
6Bhushan Power & Steel Limited,  Nova14 MWCoal
7Supersmelters Limited, West Bengal35 MWWHRB & Coal / Char / Washery
8Rungta Mines Limited, Kamanda2 x 45.5 MWCoal CFBC
9Rungta Mines Limited, Dhenkanal2 x 25 MWWHRB & CFBC
10Rungta Mines Limited, Dhenkanal Phase-II50  MWWHRB & CFBC
11Rungta Mines Limited, KaraKolha1 x 22 MWWHRB & CFBC
12Sunvik Steels Pvt. Ltd7 MWWHRSG
13Electro Steel Castings Ltd., West Bengal5MWCoke oven WHRB
14Rungta Mines Limited, Kamanda20 MWCoal
15Rungta Mines Limited, Kamanda1 x 45.5 MWCoal
16Rungta mines Chaliyama2x 20 MW
1X 20 MW2X40 MW
1X30 MW
2 X65 MW
WHRB & AFBC
WHRB
CFBC
COKE OVEN WHRB
WHRB
17MGM Minerals Limited24 MW WBRB & CFBC
18Crackers India Alloys Limited10 MWWHRB & AFBC
Total584.5 MW